Commercial electrician, Moulton

Commercial Electrician in Moulton, TX

Commercial electrical maintenance, repairs and projects for Moulton facilities, from our shop in Round Rock.

Something down right now? Call (737) 301-4536

Permits and inspections in Moulton

Our electrical contractor license (TECL #39622) is statewide. We file the permit, handle the utility paperwork and meet the inspector.

  • 01

    Who issues electrical permits: City of Moulton, City Hall at 102 S. Main Street. Commercial work inside city limits needs a Commercial Development Permit under Article 3.08 of the city code (Ordinance No. 03142013-009). No online portal was found.

  • 02

    How to apply: The property owner submits a Commercial Development Permit Application with a $25 fee. The ordinance requires a list of all contractors and subcontractors with copies of their state licenses (including the electrical license), floodplain information, approved county or state permits, start and finish dates, contact information for the project team, project utility needs and estimated service connection requirements, infrastructure impacts such as temporary power, erosion control and detention plans, and a traffic control plan. The rule covers any commercial new construction, renovation or improvement.

  • 03

    Inspections: The ordinance says the city performs and requires no inspections. Copies of any third-party inspections the owner or contractor gets must be given to the city as they are received.

  • 04

    What to know locally: Because Moulton does not inspect, it does not issue certificates of occupancy unless a Texas-licensed architect or engineer sends the city a stamped, signed and sealed letter certifying that city, state and adopted building code requirements were met and inspected. Plan to hire a third-party inspector so you have reports to give the city. The city code is on Franklin Legal, with the ordinance posted on eCode360.

  • 05

    Utility coordination: City of Moulton (city-owned electric service). The city says it provides electric, water, sewer and trash service, and its Public Works department maintains the electric system. New service starts with the city's Utility Service Connection Application at City Hall. The commercial permit application must state the project's utility needs and estimated service connection requirements, plus any temporary power connections.

  • 06

    Typical review time: Not published by the city.

Moulton questions

  • 01

    Does Moulton inspect commercial electrical work? No. City ordinance says no inspections are performed or required, but copies of any third-party inspections must be given to the city.

  • 02

    How do I get a certificate of occupancy in Moulton? A Texas-licensed architect or engineer must send the city a sealed letter certifying the building meets city, state and adopted code requirements.

  • 03

    What does the Moulton commercial permit cost? The ordinance sets a $25 development permit fee, paid with the application.

Recent work near Moulton

Our recent projects are in Austin, Round Rock and Burnet. See the case studies.

Moulton facility? Start with the assessment.

You get a ranked list of what needs attention, budget ranges and a written scope. If there is a fee, it is credited toward the work when you approve within 30 days.

Where the work is. We serve facilities within about 60 miles of downtown Austin.

A rough estimate is fine.

If yes, we'll ask you to send them after we talk.

Helps us send the report to the right people.

Or call (737) 301-4536.

Sources

Permit and utility facts checked 2026-11-02 from: ecode360.com cityofmoulton.com cityofmoulton.com cityofmoulton.com. Rules change; we confirm them on every permit.