Entegris: Office Lighting Replacement in Burnet

Industry

Semiconductor materials

City

Burnet

Electrical scope

Removed the existing office light fixtures, furnished and installed new LED fixtures, and hauled away and disposed of the old ones.

Timeline

Awarded in April 2026, with work starting in late September 2026. We held the material pricing from award to start, so the five-month wait cost the client nothing extra. Installed in phases, with the fixture swaps done on weekends so the offices stayed in use during the week. Finished in October 2026.

Electrical outcome

Clean, thorough work in occupied offices. Work areas were cleaned up after every shift, our crew removed and disposed of the old fixtures, and every new fixture was checked before we left.

He was very mindful of my property, kept his workspace clean, and his attention to detail really stood out.

Google review, semiconductor materials client